Week Date Topic Project Assignment / Due Date
1 22 August
Introduction
Life Cycle
 
2 29 August Life Cycle

Systems Analysis

 
3 5 September
Systems Analysis
9/5 Project 1: Topic, Client and High-Concept Statement
4 12 September Scenarios & Screen Design 9/14 Project 2: Systems Analysis
5 19 September
Scenarios & Screen Design
 
6 26 September Rapid Prototyping 

Benchmark Tasks

9/28 Project 3: Scenarios, Screen Design
7 3 October
Benchmark Tasks 

Evaluation (Intro)

Evaluation before Data Collection

 
 8 10 October Evaluation During and After Data Collection 

Benchmark Tests

17 October  Interaction Design Guidelines

Web Intro, Guides, UAF-Guides

10/17 Project 4: Benchmark Tasks and Prototype

Prototype Demos Outside class

10 24 October Interaction Design Guidelines

Web Intro, Guides, UAF-Guides

 
11 31 October
Interaction Design Guidelines:Web Intro, Guides, UAF-Guides

Usability Inspection

12 7 November
User Action Framework Demos

Usability Concept Classification

13 14 November Project Presentations 11/14 Project 5: Formative Usability Evaluation Groups that are doing presentations on this day will have until 5:00 pm on 11/15 to turn the project in.

11/14 Project 6: Oral Project Presentations by Groups 1, 2, 3, 6

11/16 HW#1 is due. People in groups that are doing presentations on this day will have until 5:00 pm on 11/17 to turn the HW in.

11/16 Project 6: Oral Project Presentations by Groups 4, 5, 7, 9

   
Thanksgiving Break
 
14 28 November Project Presentations 11/28 Project 6: Oral Project Presentations by Groups 10, 11, 12, 13

11/30 HW#2 is due. People in groups that are doing presentations on this day will have until 5:00 pm on 12/1 to turn the HW in.

11/30 Project 6: Oral Project Presentations by Groups 14, 15, 16, 17 

15 5 December Wrap-up and Review 

Faculty Evaluations (attendance required)

12/5 Project 7: Team Member Evaluations
  8 December FINAL EXAM, 7:45AM (Friday)  FINAL EXAM